six_storey_Six-storey Housing using Light Steel Framing and bathroom Modules_left

Mixed light steel framing and modular construction was selected for The Peabody Trust's housing project at Lillie Road, Fulham, because it satisfied the client's requirements for speed of construction, improved quality and reliability by off-site manufacture. Specialist constructor, Forge Llewellyn Ltd (now The Forge Company), and consulting engineer, Michael Barclay Partnership, conceived a mixed panel and modular structure, in which all the components were pre-fabricated using light steel C sections.

The project consists of 65 apartments, each of approximately 50 m2, constructed in three blocks, the largest of which is 6 storeys high. It is on the site of a former school, and for this inner city locality, reduced disruption due to the construction operation was an important client criterion in the choice of methods of construction.

Six-storey Housing using Light Steel Framing and bathroom Modules

SCIThe construction period was reduced to 68 weeks, a saving of 16 weeks on blockwork or concrete construction. Bathrooms were pre-fabricated as modules, which were fully fitted out before delivery to site. The blocks all have a semi-basement car park in Slimflor construction. Some exposed or expressed steel elements were used, but the majority of the structure was prefabricated using light steel wall and floor panels.

This high level of pre-fabrication allowed the building to be constructed rapidly, and safely, by using the floors as working platforms.

Six-storey Housing using Light Steel Framing and bathroom Modules

All partners in the project operated under the new PPC 2000 agreement, which encourages ‘open book' and non-adversarial relationships. A high level of thermal and acoustic insulation was provided in the building fabric to meet Parts E and L of the revised Building Regulations (2002).

Architects, Feilden Clegg Bradley, also continued the theme of pre-fabrication by choosing a lightweight stack-bonded terracotta tiling system as a ‘rain-screen' façade. Aluminium rain-screen cladding was used at higher levels. A sedum roof on the lower blocks reinforces the green landscape.

Construction details

The 6-storey building is made from pre-fabricated light steel panels, floor cassettes, and bathroom modules, all using standard light steel C sections. The wall panels resist vertical and horizontal loads applied to the building, making this building the tallest in the UK using light steel framing as the load-bearing structure. Robustness issues are important for this height of structure, and the structural designer, Michael Barclay Partnership, used SCI's recommendations for tying action to achieve a robust efficient design. Various accidental loading scenarios were also examined, involving removal of whole panels, and the analysis showed that the structure was stable and robust to these extreme events.

Rectangular Hollow Section (RHS) members were introduced as ‘expressed' steelwork on the end façades, and also in the balconies. They were installed along with the light steel framing panels.

The bathroom modules were also designed to be structural so that their walls and floors contribute to the resistance to loads. The floor elements used 200 mm deep C sections, and the wall elements used 100 mm deep C sections in 1.2 mm to 2.4 mm thickness, depending on the loads applied. Floors were pre-assembled as cassettes. Cross-walls were braced by cross-flats for stability.

The separating floors and walls achieve an airborne sound reduction of over 63 dB, by use of mineral wool and sound resistant plasterboard by Lafarge. Resilient bars support two layers of plasterboard ceiling. This construction satisfies the new Part E requirements of the Building Regulations.

Various energy efficiency measures were introduced in order to minimise the operation cost of the building, and dwellings will be individually metered. The external walls achieve a U value of 0.2 W/m2°C for excellent energy efficiency by placing mineral wool between the studs and also external to the wall. This U value is significantly less than in the new Part L requirements of the Building Regulations.

Summary
Architect Fielden Clegg Bradley
Structural Engineer Michael Barclay Partnership
Constructor Walter Llewellyn
Light Steel Framing The Forge Compnay, Ayrshire Steel Framing
Design of bathroom pods MTech
City Fulham
Country UK
Region Europe
Climatic Condition Temperate
Housing Type Multi-family high rise
Key information
Number of storeys 6
Living area (m2) 50 m2
New-build home yes

 pdf   Six-storey Housing using Light Steel Framing and bathroom Modules

 

Comments
Search
Only registered users can write comments!

3.26 Copyright (C) 2008 Compojoom.com / Copyright (C) 2007 Alain Georgette / Copyright (C) 2006 Frantisek Hliva. All rights reserved."